At Plant High School in Tampa, three large temporary air conditioning units pump cold air into the gym. The air conditioning unit at the school failed and the three units were brought in as a band aid.
Plant is not the only school in the county with air conditioning problems. In fact, the school isn’t even on a list of 38 other schools in the county that need major A/C repairs.
The total cost of all of the repairs needed at the schools is more than $343 million and Hillsborough County School Superintendent Jeff Eakins says the county just doesn’t have the money needed to fix everything.
“We definitely have a great need and the revenue coming in just isn’t going to be able to fulfill that need immediately,” said Eakins.
During the summer, the school district worked to repair or replace 10 air conditioning systems at schools, but that only scratches the surfaces of the critical needs repair list.
Hillsborough County School Board members say the fault lies with Tallahassee where legislators have refused to adequately fund education.
“Hopefully Tallahassee hears the message. I think we’ve been very loud and clear on the fact that we’ve not been able to get funding the way that schools need to be funded,” said School Board Chairman Sally Harris.
Jeff Eakins maintains if the legislature won’t send the money, the county may have to explore other sources of revenue to make badly needed repairs.
“It could be anything from a sales tax, it could be a millage increase on property tax, there’s different ways other communities have gone about acquiring additional revenue,” said Eakins.
List of Hillsborough County Schools air conditioning projects
Air Conditioning Projects Complete in Summer 2018
B.T. Washington, Crestwood, Edison, Gorrie, Morgan Woods, Williams, Wilson, Roosevelt, Rodgers, Cypress Creek
Schools in Need of Immediate Air Conditioning Overhauls or Replacements
Air Conditioning Projects for 2018-19 (total $95,756,000)
- Potter Cafeteria Air Conditioner $622,000
- Walden Lake Complete Replacement Excluding One Wing $9,747,000
- Colson Complete Replacement Excl. One Wing & Chiller Plant $5,648,000
- Folsom Airside and Controls $5,418,000
- Lithia Springs Airside and Controls $5,753,000
- Lowry Airside and Controls $7,057,000
- Knights Complete Replacement $7,122,000
- Schwarzkopf Airside and Controls $5,452,000
- Dickenson Complete Replacement $5,561,000
- Durant Airside and Small Chillers $17,770,000
- Burnett Complete Replacement $10,472,000
- Lincoln Complete Replacement $4,564,000
- Benito Complete Replacement $10,570,000
- Air Conditioning Projects for 2019-20 (total $138,550,000)
- Blake Airside and Chillers $15,576,000
- Dunbar Complete Replacement $3,168,000
- Sickles Airside and Chiller Plant $18,465,000
- Walker Airside, Chiller Plant & Controls $10,183,000
- Wharton Airside Chillers and Controls $21,198,000
- Clark Airside, Chillers and Controls $7,094,000
- Riverview HS Chiller Plant, Airside and Controls $17,805,000
- Rodgers 2 Chillers, Airside and Controls $9,641,000
- Valrico Complete Replacement $8,242,000
- Adams Complete Replacement $10,994,000
- Lavoy Complete Replacement $3,613,000
- Pizzo Complete Replacement $6,217,000
- Robinson ES Complete Replacement $6,354,000
Air Conditioning Projects for 2020-21 (total $108,759,000)
- Westchase Complete Replacement $8,399,000
- Young Selected Buildings $7,500,000
- Bevis Complete Replacement $6,625,000
- Gibsonton Complete Replacement $6,378,000
- Dr. Carter G. Woodson Complete Replacement $14,843,000
- Memorial Airside and Controls $8,693,000
- Pierce Complete Replacement $9,166,000
- Pride Complete Replacement $6,390,000
- Rampello Airside and Controls $7,909,000
- Randall Complete Replacement $9,337,000
- Robinson HS Complete Replacement $16,616,000
- Sulphur Springs Selected Buildings $6,903,000